Week Commencing 15th June
Work continues this week from the jack-up platform cutting away and shaping the existing concrete at the end of the launching slipway.
The new pre-cast sections of slipway are gradually being placed at the bottom of the steel slipway.
Work will continue this week on the assembly of the hydraulic tipping cradle in the boathouse.
|