Sennen Cove Lifeboat Station
Construction Works during 2009

THIS WEEK`S PLANNED WORKS

Week Commencing 23rd February

Plans for this week include continuing preparation of the granite plinths to take the new pre-cast concrete piers which will hold the new launch slipway. Works will continue in the boathouse to excavate an area of the boathouse floor in preparation for a base for the new
hydraulic tipping cradle.

Construction of a temporary access slipway into the boathouse from the old slipway to the west of the short slipway is also planned for this week, with demolition of the short slipway commencing when this temporary structure is complete.

Again during this week it is anticipated that only small amounts of spoil will be pulled over Cove Hill using a small dumper.

 

 

25th February
The two winch drums and winch motor unit loaded onto a lorry to go off for refurbishment this morning.

The lifeboat station looks odd without the long slipway - the short slip looks quite normal for a lifeboat station except that there is no sea anywhere near it !!
The works to construct a temporary access to the station doors from the harbour slip continued this week.
The `Norman Salvesen` continued to enjoy the unseasonally fine sea conditions on the moorings.




Lifeboat Home Page Construction Works Home Page Sennen Cove Home Page
Lifeboat Stations - if we are not linked to your website then we should be !
e-mail your url
(Links to any lifeboat / marine S.A.R. site always welcome)

The Royal National Lifeboat Institution is a Registered Charity - number 209603

The Lifeboat section of the sennen-cove website is independent of the R.N.L.I. and as such is not endorsed by the Institution. The website is maintained by current crew members of the Sennen Cove Lifeboat.
Disclaimer About this site Privacy Contact Webmaster
© terry george 2001 - 2009