Week Commencing 27th April
Work is continuing this week on the internal floor of the boathouse.
A final concrete pour is due at the end of the week or early next week on the floor out to the boathouse doors.
On Wednesday 29th, the last of the precast sections forming the pillars for the launch slipway was placed.
Poor weather kept the Norman Salvesen at Newlyn over the weekend, returning to moorings in the Cove on Wednesday morning
|