Sennen Cove Lifeboat Station
Construction Works during 2009

THIS WEEK`S PLANNED WORKS

Week Commencing 3rd August
More of the same this week as work progresses towards completion of both slipways.
Electrical work continues within the lifeboat house and it is anticipated that final installation of the winches may commence during this week.


Series of images taken on 7th August
Top two show the final concrete pour to complete the recovery slipway concrete toe.
Above left shows the tipping cradle aligned with the launching slipway - this has now been tested and is ready for the final
concrete pour.
Above left shows the view down the launching slipway with most of the infill panels in place and just 3 more concrete
sections to go in at the far end of the slipway using divers from the platform.

Lifeboat Home Page Construction Works Home Page Sennen Cove Home Page
Lifeboat Stations - if we are not linked to your website then we should be !
e-mail your url
(Links to any lifeboat / marine S.A.R. site always welcome)

The Royal National Lifeboat Institution is a Registered Charity - number 209603

The Lifeboat section of the sennen-cove website is independent of the R.N.L.I. and as such is not endorsed by the Institution. The website is maintained by current crew members of the Sennen Cove Lifeboat.
Disclaimer About this site Privacy Contact Webmaster
© terry george 2001 - 2009