Sennen Cove Lifeboat Station
Construction Works during 2009

THIS WEEK`S PLANNED WORKS

Week Commencing 6th July
Work will continue this week from the jack-up platform, working on the underwater section of the launch slipway.
Work continues this week on removal of the temporary access works at the front of the boathouse, and work is expected to start on construction of the new recovery slipway.


 

Above images taken on 12th July show the launching slipway steelwork pretty much completed and awaiting infill panels, rollers and handrails.
The first stages of steelwork for the short recovery slipway is also in place.

Image on the left shows the tipping cradle, with preparations being made for the final concrete pour around the base.
Image on the right taken on 9th July shows work continuing on the concrete toe of the launch slipway.


Lifeboat Home Page Construction Works Home Page Sennen Cove Home Page
Lifeboat Stations - if we are not linked to your website then we should be !
e-mail your url
(Links to any lifeboat / marine S.A.R. site always welcome)

The Royal National Lifeboat Institution is a Registered Charity - number 209603

The Lifeboat section of the sennen-cove website is independent of the R.N.L.I. and as such is not endorsed by the Institution. The website is maintained by current crew members of the Sennen Cove Lifeboat.
Disclaimer About this site Privacy Contact Webmaster
© terry george 2001 - 2009