Week Commencing 7th September
The contractors are now entering a `completion and tidying-up` phase.
The main issue remains the removal of the jack-up platform - this requires quiet sea condtions and this week does not really promise a major opportunity - though possible Wednesday / Thursday may be a chance.
Images below show the `state of play` on Sunday 6th September
Five crew members from the Cove will be in Poole this week on a Machinery course for the new lifeboat.
|